Thanksgiving looked different across New Jersey this year.
As families and friends prepared holiday meals and gathered around Thanksgiving tables, a strong coastal storm brought high winds, heavy rain and coastal flooding to parts of the state. For thousands of our customers, the storm also brought an unwelcome disruption: power outages.
But being Jersey Ready means being prepared for whatever Mother Nature sends our way, even on a holiday. Nearly 3,000 of our employees, contractors and support personnel responded, restoring power to more than 127,000 customers by 8:28 a.m. Saturday, Nov. 28.
For our employees working through the holiday, Thanksgiving meant stepping away from their own families to help bring power back to yours – we are deeply grateful to all of them.
We know losing power is difficult — and is especially disruptive during a holiday. We’re thankful for your patience as our teams worked around the clock, often in challenging conditions, to safely restore service.
Preparing for the storm and restoring power through Thanksgiving
As forecasts grew more certain ahead of Thanksgiving, we activated our storm response plan, called in additional crews and strategically positioned personnel and equipment across our service territory.
Nearly 3,000 team members were mobilized to support response and restoration efforts, including line workers, tree crews, underground crews, substation and relay technicians, mechanics, dispatchers, gas employees, appliance service technicians, engineers, storeroom personnel, customer service representatives and many others working behind the scenes. Restoration of this magnitude requires extensive coordination.
When strong winds arrived on Thanksgiving Day, our teams were ready. Crews responded to outages throughout the day, overnight and into the holiday weekend as fallen trees and branches damaged electrical equipment. Working together around the clock, employees and contractors assessed damage, addressed public safety concerns, coordinated resources and worked to restore power safely and as quickly as possible.
Throughout the response, safety remained the priority. Over the course of the storm, we restored power to more than 127,000 customers. Restoration focused on critical facilities such as hospitals and emergency response agencies, along with repairs that could restore the greatest number of customers, working our way through to help all of our impacted customers.
Our storm readiness also reflects work that happens long before severe weather is in the forecast. Over the past decade, we’ve dedicated $30 billion to utility infrastructure, with nearly 75% focused on improving reliability and resilience.
Those investments, combined with year-round planning and the dedication of employees and contractors who spent time away from their families over Thanksgiving, help us respond when customers need us most.
Why do some power outages take longer to restore than others?
We also know that when most of the neighborhood has power again and your home is still dark, every additional hour matters.
As restoration progresses, the outages that remain are often among the most complex. A tree may need to be safely removed before electrical repairs can begin. Multiple sections of wire or other equipment may be damaged. And some repairs are located in backyards or other places where trucks and heavy equipment cannot easily reach. Read more about why some outage restorations take longer than others.
Severe weather can add another challenge. High winds can restrict the safe use of bucket trucks, while flooding, fallen trees and debris can make it harder to move crews, equipment and resources into place.
Sometimes, crews also discover more than one source of damage. Repairing the equipment closest to a customer’s home does not always restore service if another damaged part of the system is preventing electricity from reaching it.
That was the case in South Orange on Thanksgiving night, where a fallen tree damaged four sections of power line and a transformer in a residential backyard. Crews first had to make the area electrically safe, then tree crews removed the fallen tree before crews could begin repairing the damaged equipment. During that work, crews identified additional damage to an underground line supplying the neighborhood — another repair that had to be completed before power could be fully restored.
We know understanding the work behind an outage doesn’t make waiting for power any easier. To every customer who was affected by this storm: thank you for your patience while our crews worked safely to get your lights back on.
Grateful for the people behind the response
Storm restoration is a team effort, and this one came at a time when many people would normally have been home with family and friends.
Instead, thousands of our employees, contractors and support personnel spent Thanksgiving serving their neighbors. They worked through wind and rain, through the night and into the days that followed.
Their work brought lights back on around Thanksgiving tables, restored heat and electricity to homes and businesses and helped communities across New Jersey recover from the storm.
“Thanksgiving is a time for family and friends, and we know this storm disrupted those plans for many of our customers. We’re grateful for their patience as our crews worked around the clock to restore power safely,” said John Latka, senior vice president, PSEG operations. “I’m incredibly proud of the employees who worked through the holiday to help our neighbors get their power back. Their hard work and dedication deserve our deepest thanks and reflect the very best of our team.”
Restoration complete — and public service continues
At 8:28 a.m. Saturday, Nov. 28, we restored the final customer affected by the Thanksgiving coastal storm.
For our customers, that marked the end of this restoration effort. But it isn’t the end of the work.
With power restored to all customers affected by the Thanksgiving storm, our crews will spend Saturday completing cleanup work and returning the system to normal operations.
With all customers restored, resources are being made available to assist other New Jersey utilities still responding to storm-related outages — extending the same spirit of public service to neighboring communities working to recover.
And don’t forget: Severe weather can happen at any time. You can learn more about storm safety and visit our outage center to learn how to prepare, report an outage and stay informed during future storms.
That is what “Public Service” means to us: preparing before severe weather arrives, showing up when our customers need us, working safely until the job is done — and helping our neighbors when we can.
To our customers, thank you for your patience and understanding.
And to the employees, contractors and partners who gave up part of their Thanksgiving to serve New Jersey: thank you for being there when it mattered most.